Reconstruction of the building intended for production of potato chips with total capacity of 25,896 tons per year was carried out in three stages.

 First stage: installation of a 1.25 t / h production line, installation of a gas boiler.

 Second stage: warehouse extension.

 Third stage: installation of a line with a capacity of 2 t / h, as well as installation of additional equipment for degreasing industrial effluents.

 The project resulted in extension of the production building and increase of the production capacity of the entire factory.